Firstly, the main building is about 90% closed in with all glass panels in place. Work in the interior of the structure is ongoing. This includes framing, mechanical, plumbing, and electrical work. In addition to this progress, the exterior brick veneere work is nearly complete on all sides of the building. Moving on to the very top of the building, the roofing membrane for the entire structure is now completed, and work on the green roof is expected to begin soon. 

Furthermore, progress on site grading is currently underway. On the north end, a new parking lot will be installed, alongside new stormwater upgrades, sidewalks, curb, and gutter on Myrover Street. Lastly, pathways and sidewalks through the park are now being constructed. As a result of this construction, the park is now temporarily closed, with fencing and signage sealing off the area to the public. We understand that this is an inconvenience and we will keep you updated as to when the park will reopen for public use. 

Additional updates will continue to be shared on our website and social media. Until then, please have a look at the image provided below highlighting our progress in recent months. We thank you all for your continued interest, patience, and support, for this project as we get closer to our opening in 2028. 

 

View of the NC History Center building looking east.